- Project Name:Beni Suef 4800 MW Combined Cycle Power Plant - Egypt
- Project Description:Engineering, Procurement, Construction, Testing, Commissioning, start- up and Civil works for 4x 1200 MW (SCCP5-8000H 4 x (2+1), WCT, Combined Cycle Power Plant
- Owner:Upper Egypt Electricity Production Company subsidiary of Egyptian Electricity Holding Company
- Project Location:Egypt
- Main Contractor:The Consortium of Siemens AG & ELSEWEDY ELECTRIC
- Commencement Date:July 2015
- Completion Date:August 2018